Wright-Patterson Air Force Base Substation B

  • Date Completed: July 2010
  • Project Location: Wright-Patterson Air Force Base, OH
  • Project Category: Government
  • Project Owner: Wright-Patterson Air Force Base
ESI operated as the general contractor on this project. The scope of work included

replacing 69-kV single phase transformers with one 20-mVA 69kV three-phase transformer. ESI also replaced overhead bussing, steel structure and gang-operated air switches, and extended an underground utility vault and replaced 15-kV walk-in switchgear. ESI spliced and extended 15-kV lead cable with EPR and updated SCADA controls and wiring.